Tag: air sealing

April 29, 2015

Upon hanging the TJI insulation cavity, the vapor open Weather Resistant Barrier (WRB) was installed and all seams were taped.  Given the pressure of the cellulose that will be blown-in behind this WRB, we decided to use Solitex Mento 1000 and taped with our favorite Tescon Vana tape.
mento and tape blog
The next layer is the ventilation cavity / rainscreen / furring strips.  We decided on horizontal with vertical furring strips to keep the cellulose bulge in check and maintain an acceptable ventilation cavity as well as provide a more substantial nailing surface for our engineered wood siding.

November 5, 2014

framing 2
And suddenly…it’s a house.  The trusses arrived and were set at 24″ on center on top of our 24″ on center 2×6 structural wall on top of our 24″ on center MSR 2×10 floor framing on top of our basement wall.  Walking through the skeleton to see the clean, aligned bones was really exciting.  Our framers did a fabulous job with advanced framing and aligning all the structure.  It sounds simple and straightforward, but I’ve walked in many that seem junked up with unnecessary studs and multiple upon multiple jacks and kings.
framing 1
The blue line along the top plate is Tescon Vana magic tape sealing the corner edge of our plywood air barrier. Each spliced top plate is taped as well.
Next comes the roof sheathing, finalizing the plywood air barrier and taping all the seams.